HomeMy WebLinkAbout09-17-1998 DOVC MEETING PACKETl
r;*A*) \,
CONTRA COSTA COUNTY
DOUGHERTY VALLEY OVERSIGHT COMMITTEE
WILL MEET ON SEPTEMBER 17, 1998
AT 1:00 P.M.
AT SAN RAMON CITY HALL
PLANNING CONFERENCE ROOM
2222 CAMINO RAMON
SAN RAMON
AGENDA
1. PUBLIC COMMENT.
2. REVIEW AND RECOMMENDATION TO THE COUNTY ZONING
ADMINISTRATOR ON SHAPELL INDUSTRIES AND WINDEMERE RANCH
PARTNERS ANNUAL COMPLIANCE REPORTS. (County Staff)
3. UPDATE ON BOL -JNGER CANYON ROAD CULVERT CROSSING.
(Shapell Industries)
For more information, contact Debbie Chamberlain at (925) 335-1213.
Staff Review, Annual Compliance Reports
(Dougherty Valley Settlement Agreement)
Prepared by CDD Staff, September 9,1998
The Dougherty Valley Settlement Agreement requires Shapell Industries and
Windemere Ranch Partners to submit an annual compliance report by October 15 of
each year. The report should detail the proceeding year's construction activities
(October to October). and their anticipated construction activities for the next three
years. Additionally, with the recent construction activity, staff will report on the
Community Facilities Fee account in relation to the number of building permits
issued for residential construction. These reports, including the following staff
evaluation of the compliance reports, are then forwarded to the Dougherty Valley
Oversight Committee for recommendation to the County Zoning Administrator for
consideration at a noticed public hearing to be held by January 30,1999.
Overview of Compliance Evaluation
Staff has evaluated the Annual Compliance Reports for the 1998 Project year
(October 1997 to October 1998), as submitted by Windemere Ranch Partners
and Shapell Industries of Northern California, in compliance with the annual
reporting and review requirements of the Dougherty Valley Settlement
Agreement, Appendix G.
A. Compliance with Performance Standards
Both Shapell and Windemere provided the information required by Appendix
G, and both provided it in a timely manner.
Staff has reviewed this information and finds that both Shapell and
Windemere appear to be in compliance with the requirements of the
Settlement Agreement, as set forth in Appendix G.
B. Progress in addressing "Intermediate Steps:
Intermediate steps include those activities that lead to compliance with each
CIP performance Standard. These are in essence planning milestones
designed to help ensure timely compliance. Staff has reviewed the Annual
Reports and finds that both Shapell and Windemere appear to be in
compliance with these intermediate steps, as set forth in Appendix G.
C. Third Party consistency with Settlement Agreement: No sustained
problems encountered with third parties.
DVSA Annual Compliance Report
September 9,1998
Staff Recommendations
Page 2
A. On -going failure to comply by Developer: Staff identified no on -going
failure to comply, on the part of the Developers.
B. On -going failure to comply by someone other than developer: Staff
identified no on -going failure to comply, on the part of parties other than the
Developers.
C. Recommended measures to ensure compliance with Performance
Standards and Intermediate Activities: Staff has identified no on -going
compliance failures and thus staff has no recommended measures.
DVSA Annual Compliance Report Page 3
September 9,1998
Attachment A: Detailed Compliance Review
Summary of Construction Status:
• Shapell has completed most of the mass grading for Phase I (Bridges at Gale
Ranch) project. By August 1,1998, the County had issued Shapell 76 building
permits, of which 51 were for habitable units and 15 were for models. No homes
are occupied. By fall, 1998, Shapell expects to complete most of the Golf Course,
to pave two more subdivisions (three are already paved), to complete most of the
Elementary School Site mass grading, and to begin construction of the club
house. Two hundred and forty-two lots have been final mapped.
• Windemere has not yet commenced construction, but expects to by the spring of
1999. Windemere expects the first housing units to be available in 2000.
Detailed Analysis of Compliance with Performance Measures:
I. Child Care Facilities:
Summary: Provided with each elementary school. First delivery date is
projected to be September, 2000. Dates for additional 3 facilities are more
than three years in the future.
Compliance Status:
• Shapell: Shapell is providing the first elementary school, the first non-profit
childcare center (at the school site), and site improvements for a second child-
care facility at a commercial site. The site is being prepared for the non-
profit facility.
• Windemere: No action required.
Near term dates:
• January, 1999: Planning Complete (SRVUSD)
• September, 1999: Shapell start construction.
II. Community Center
Summary: Delivery date projected to be 2003 (3,666th building permit), with
planning starting in 2001. Funded from the County's Capital Facilities Fee
and from the Developers.
Compliance Status: No actions required.
Near term dates: None
DVSA Annual Compliance Report
September 9, 1998
Page 4
III. Developed Parkland
Summary: Develop 6.5 acres of parkland per 1,000 population, with about
half being for neighborhood or community parks.
Compliance Status:
• Shapell: Project 1,000 residents by the year 2000. Currently grading North
Chanterelle Park (7.5 acres). Expect to construct in Spring, 1999.
• Windemere: Preliminary drawing done. Projected completion date for first
parks is 2001.
Near term dates:
• Spring, 1999: Shapell, Start construction on No. Chanterelle Park.
IV. Corporation Yard
Summary: Site has been located and approved by the County and City of San
Ramon. Delivery date not yet established.
Compliance Status:
• Shapell: Suggested site approved. Final design will be incorporated into
the Final Development Plan application for Phase IV. Schedule will be
determined by the County, after discussion with the City, when development
is approximate to that area.
• Windemere: no action required.
Near term dates: None.
V. Fire Stations:
Summary: No interim stations required. First and only permanent station
required prior to initial occupancy in Windemere (Year 2000).
Compliance Status:
• Shapell: No action required yet.
• Windemere: No action required yet.
Near term dates:
• 1998/1999: Windemere initiate planning tasks
• 1999 Windemere initiate construction
VI. Flood Control Facilities
Summary: Detention facilities established with each tentative map
application.
Compliance Status:
• Shapell: Shapell's Phase I basin is already built.
Windemere: Schedule set with tentative map. Construction will commence
with grading.
Near term dates:
0 Spring, 1999: Windemere construction to start w/ grading.
DVSA Annual Compliance Report
September 9,1998
Page b
VIL Library
Summary: Delivery date projected to be 2003 (3,666th building permit), with
planning starting in 2001. Site and size have been determined.
Compliance Status: No actions required.
Near term dates: None
VIII. Staging Areas for Open Space
Summary: Each developer to provide an open space staging area; schedule to
be determined by the county.
Compliance Status:
• ShapeM Location established in DVSP; part of Phase IV or later, timing
uncertain.
• Windemere: Location established in DVSP; part of Windemere Phase IV; no
actions necessary now.
Near term dates: None.
IX. Park and Ride Sites
Summary: Numbers and locations determined by the Specific Plan. Tinning
not yet determined.
Compliance Status:
• Shapell: No action with Phase I; one park -and -ride lot with Phase 11.
• Windemere: Two park -and -ride lots with Phase I; reassess need with each
subsequent phase.
Near term dates: County to determine 'schedule prior to commencement of
Windemere phase I grading.
X. Police Station
Summary: Interim facility not needed. Location of permanent facility
confirmed for the Village Center. Delivery date not yet determined.
Compliance Status: No actions required yet.
Near term dates: none
XI. Satellite Post Office
Summary: Developers' to make space available; County to established
delivery date.
Compliance Status: No actions required yet.
Near term dates: None
DVSA Annual Compliance Report
September 9,1998
Page 6
XII. Schools:
A. Elementary School
Summary: Four elementary schools required. First school delivery date is
projected to be September, 2000. Dates for additional facilities are more
than three years in the future.
Compliance Status:
• Shapell: Shapell is funding and building the first elementary school.
Site preparation on schedule; working with SRVUSD.
• Windemere: No action required.
Near term dates:
• January, 1999: Shapell complete planning (or sooner).
• September,1999: Start construction (or sooner)
B. Middle School
Summary: Two middle schools required. First middle school required at
about 6,000 units, projected to occur in more than seven years.
Compliance Status: No action required yet.
Near term dates: None
C. High School
Summary: One high school required at 1466 students (more than 6,000
units), projected to occur in more than seven years.
Compliance Status: No action required yet.
Near term dates: None
XIII. Senior Center
Summar : Provide facility before 8,607th building permit, projected to occur in
the far term.
Compliance Status: No actions required yet.
Near term dates: None
W;nciemere Ranch Partners
do Chapman & Wilson
1350 Treat Blvd., Suite 560
Walnut Creek, CA 94596
phone (925) 933-1405
fax (925) 933-1404
July 28, 1998
Ms. Debbie Chamberlain
Contra Costa County
Community Development Department
651 Pine Street — 2°4 Floor North Wing
Martinez, CA 94553
RE: Annual Compliance Report — Developer Status Reports
Dear Debbie:
Pursuant to Section IV.A of the May 11, 1994 Agreement to Settle Litigation, Windemere is
required to prepare and submit to the County a development status report outlining the
following activities:
• Construction activities that have occurred during the previous year;
• Work underway; and
• Anticipated efforts for the following three years.
In addition, you have requested that Windemere review Schedule I of Exhibit G and address
each of the performance items contained in that schedule. Our review is summarized below.
Section IV.A Activities:
1. Construction activities that have occurred during the previous year - Windemere has
not yet commenced construction. There are no activities that need reporting for this
section.
2. ' Work Underway — Although there are no construction activities underway,
Windemere is proceeding with substantial planning and public works efforts.
Windemere is processing grading plans for the first phase of development and
Windemere has recently revised its first phase tentative map to conform to prior
conditions of approval.
3. Anticipated efforts for the following three years - It is Windemere's intention to
commence grading of the first phase in April 1999. Also during 1999, Windemere
anticipates to process the next phase tentative map. The first housing units should be
available during the year 2000. Windemere expects annual absorption to equal 500 to
600 units per year. By the end of the three-year time period (2001) approximately
1,000 to 1;200 units should be constructed.
Ms. Debbie Chaberlain
July 29, 1998
Page 2
Schedule I — Exhibit G Performance Dates:
A. Child Care — The Facility is to be provided concurrently with the first elementary
school. At least 18 months prior to the delivery of the school facility, funding
mechanisms must be identified and the design/construction schedule must be
established.
It is understood that Shapell is currently designing the first elementary school.
According to the Agreement to Settle Litigation, the second school mill be required
to be operational when 1083 students have been generated. Given a student
generation rate of .3 students per detached household and A students per attached
household and assuming that 25% of the dwelling units are attached, the next school
will be required when 4,332 units are constructed. Given that Shapell's anticipated
buildout is 200 to 300 units per year and Windemere's is 500 to 600 per year,
several years remain before either funding or design must commence.
B. Community Center — The Community Center is to be provided prior to the 3,6664
building permit. At least 18 months prior to delivery, funding mechanisms must be
identified and the designlconstruction schedule must be established.
If it is assumed that Shapell will construct an estimated 500 units prior to the
delivery of the first Windemere units, and if it is assumed that the Dougherty Valley
absorption will average 800 units per year (500 to 600 for Windemere and 200 to
300 for Shapell), the 3,666th building permit should be issued in the year 2003.
Basic funding for the facility was established in 1996 when the County approved
the Development Agreements with Shapell and Windemere. Those Agreements
established a per -unit Capital Facilities fee that will be collected by the County for
funding of the community facilities.
C. Developed Parkland — Windemere is required to provide 6.5 acres of parks per
1, 000 residents. Acreage is to include a minimum of 3.0 acres per 1, 000 residents
of neighborhood or community parks. At least 18 months prior to completion, the
probable service provider is to be identified and the designlconstruction schedule
must be established. At least 12 months prior to completion, the service provider is
to be determined.
Both the Agreement to Settle Litigation and the CSA M-29 MOU identifies the City
of San Ramon as the service provider. Preliminary design for the parks within
Windemere's first phase was included in the tentative map package and working
drawings will be provided at final map.
2
Ms. Debbie Chaberlain
July 29, 1998
Page 3
D. Corporation Yard --The delivery date of this facility is to be determined by the
County. Its approximate location is to be determined by the second Annual
Compliance Review. At least 18 months prior to delivery, funding mechanisms
should identified and the design/construction schedule must be established.
The location of the facility has already been determined by the County. The
delivery date is yet to be established.
E. Fire Station - Interim and Permanent - The fire station must be delivered prior to
initial occupancy on the Windemere property. At least 18 months prior to delivery,
a f nding mechanism must be identified and the design/construction schedule must
be established
it was determined in the 1996 Specific Plan Amendment process that an interim
station would not have to be provided if a permanent station could be provided prior
to occupancy. Windemere's initial occupancy is scheduled for the year 2000.
F. Flood Control Facilities - The delivery of theflood control facilities is to be
determined by County in consultation with CCCFCWD. At least 18 months prior to
delivery, a funding mechanism must be identified and the design/construction
schedule must be established.
The delivery of the flood control detention basins for Windemere's first phase was
determined during the tentative map process. Construction will be funded by
Windemere and construction will commence with grading.
G. Libra - The library must be provided prior to the issuance of the 3, 666`h building
permit. At least 18 months prior to delivery, a funding mechanism must be identified
and the design/construction schedule must be established
Please see comments for Community Center.
H. Staging Areas - Delivery of the Staging Area is to be determined by County in
consultation with open pace operator prior to approval of the first adjacent
tentative map.
The Staging Area is located in Windemere's fourth phase of development.
I. Park and Ride Sites - Delivery of the park and ride sites is to be determined by the
County.
Windemere has two park and ride sites located within its first phase. As part of the
tentative map process, Windemere was conditioned to reserve right of way. Within
each phase of the project, Windemere was conditioned to review the need and
3
Ms. Debbie Chaberlain '
July 29, 1998
Page 4
construct the facilities as necessary subject to the review and approval of the County
Public Works Department.
J. Police Station — Delivery of a police station is to be determined by Sheriffs Department. The approximate location of the facility is to be determined at the
approval of the Trst tentative map. At least 18 months prior to delivery, a funding
mechanism must be identified and the design/construction schedule must be
established
The police station is to be located within the Village Center area. The timing for
delivery of the station is not yet determined.
K. Satellite Post Office — Delivery of the facility is to be determined by County through
consultation with US Postal Service. Where are no dates associated with funding
or design.
Windemere will comply with the requirement at the appropriate time.
L, Elementa Schools — Schools are to be provided according to student generation
rates or as otherwise required by SRVUSD. A financing and cost distribution plan
for construction and equipment are to be established prior to recording a f nal map
encompassing the school site. A design/construction schedule is to be established
36 months prior to the estimated delivery of the facility.
Please refer to the comments regarding Child Care.
M Middle School - The first middle school must be provided prior to August 1' of the
year that the project generates 733 6-8 grade students, or as otherwise required by
SRVUSD. The second middle school is required when the project generates 1,833
students. A financing and cost distribution plan for construction and equipmentare
to be established prior to recording a final map encompassing the school s
design/construction schedule is to be established 36 months prior to the estimated
delivery of the facility.
Given a student generation rate of .15 students per detached household and .03
students per attached household and assuming that 25% of the dwelling units are
attached, the first school will be required when 6,108 units are constructed. Given
that Shapell's anticipated buildout is 200 to 300 units per year and Windemere's is
500 to 6001) several years remain before either funding or design must commence.
N. High School — A high school must be provided prior to August I" of the year that
the project generates 1466 9-12 grade students, or as otherwise required by SRVUSD. A financing and cost distribution plan for construction and equipment
are to be established prior to recording a final map encompassing the school site.
4
Ms. Debbie Chaberlain
July 29, 1998
Page 5
A design/construction schedule is to be established 36 months prior to the estimated
delivery of the facility.
Given a student generation rate of .25 students per detached household and .05
students per attached household and assuming that 25% of the dwelling units are
attached, the high school will be required when 7,330 units are constructed. Given
that Shapell's anticipated buildout is 200 to 300 units per year and Windemere's is
500 to 600, several years remain before either funding or design must commence.
O. Senior Center — A senior center must be provided prior to the issuance of the
8, 607`h building permit. At least 18 months prior to delivery, a funding mechanism
must be identified and the design/construction schedule must be established
If it is assumed that Shapell will construct an estimated 500 units prior to the
delivery of the first Windemere units, and if it is assumed that the Dougherty Valley
absorption will average 800 units per year (500 to 600 for Windemere and 200 to
300 for Shapell), the 8,607th building permit should be issued in the year 2010.
Basic funding for the facility was established in 1996 when the County approved
the Development Agreements with Shapell and Windemere. Those Agreements
established a per -unit Capital Facilities fee that will be collected by the County for
funding of the community facilities
If you have any questions regarding the above, please do not hesitate to call.
Sincerely,
6--1
F. Allan Chapman
Agreed and Approved:
-�/L hD �9u
Oc Date
5
flue-uS-W wtu 11: 1 d b 1 NU LHNV Vtr 1 MA 14U. 4une4o400 ( r. u 1
SHAPELL INDUSTRIES of NORTHERN CALIFORNIA
A Division of Shapelt industries, Inc.
August 1, 1998
Ms. Debbie Chamberlain
Senior Planner
Community Development Dept.
Contra Costa County
651 Pine Street
North Ong, Fourth Floor
Martinez, CA 94553
Re: Gale Ranch
Settlement Agreement Annual Compliance Report
Dear Ms. Chamberlain:
As required by the May 112 1994 Agreement to Settle Litigation (Exhibit G), the
Dougherty Valley developers must submit to County staff prior to October 15th of each
year a "Status Report" for their respective developments. The status reports shall outline
the construction activities that have occurred during the previous year, work underway
and anticipated efforts for the following three years. The status report shall also include
all significant activity relating to public and private infrastructure, and all. significant
residential and comuanercial activity. This year you have asked for the report prior to
August 3,1998 and to include a review of Schedule 1 of Exhibit G.
The followings the status for the Gale Ranch project as of August 1, 1998:
1. CONSTRUCTION ACTIVITIES THAT HAVE OCCURRED DURING THE
PREVIOUS YEAR:
* The mass grading of the project was delayed by weather from October 1997 until the
fast week of June, 1998. The mass grading continues, it is approximately 80% complete
as of August 1, 1998. The majority of the work remaining is in the northeast quadrant of
the site.
* Golf course construction started in June of 1998. It is only 35% complete as of
August 1, 1998. The schedule is to have all of the course seeded by November 1, 1998.
If that schedule becomes unattainable, golf holes 8, 9 and 10 may require an erosion
control hydroseed treatment to protect the course during the winter.
* Site development activities continued. Three of the first four final mapped
subdivisions were paved. in October/November 1997. Subdivision 7981(45 lots) should
be paved in August or September of 1998. Site development activities in Subdivision
8027 continue with a goal of paving those 51 lots in October 1998. 191 lots were Final
mapped in 1997; 51 lots have been final mapped in 1998.
r
.Huu ut-ytj wtu t1-le 51NU LAND DEF] rHn nu. 4u0U4040or r.uc
* Home-building commenced in late 1997. There have been 15 model permits issued
and 61 production building permits issued. There have been no residential occupancies
as of August 1, 1998. The first residential occupancy is scheduled for mid -October 1998.
* The clementary school site grading is 90% complete.
1A. SIGNIFICANT PLANNING ACTIVITIES THAT HAVE OCCURRED DURING
THE PREVIOUS THREE YEARS:
* The County Service Area has been formed and funding established through both a
tax election and benefit assessment.
* A Memorandum of Understanding has been executed between the County, City of
San Ramon and the Dougherty Valley developers outlining the implementation
responsibilities of all parties during the course of project construction.
* Architectural approval and site plan approval has been coordinated with the County
and City (in accordance with the MOU) for the single family detached Fairway Series,
the Crest Bridge Series and the Glen Bridge Series. The townhouse project, Cedar
Bridge, and the Falcon Bridge apartment condominium project has also been approvcd.
The sales pavilion and golf course clubhouse was also processed through the County with
City participation.
* The first annexation of Dougherty Valley property into the City of San Ramon is
before the Contra Costa County LAFCO on August 12,1998. The proposed annexation
includes our first four final mapped subdivisions. Subdivisions 7796, 7979, 7980 and
7981 include 191 residential lots and the public streets and infrastructure to serve them.
2. WORK UNDERWAY:
* The mass grading continues. The goal is to complete all grading within the golf
envelope by September 15, 1998, and all mass grading by November 15, 1998. The
prolonged `Il Nino" winter continues to effect the grading with heavily saturated soils in
the keyways.
* Site development activities continue in subdivision 7796, 7981 and 8027.
Subdivision 7981 should be paved in late August or early September. The underground
installation continues in Sub. 8027. Sub. 8027 is scheduled to be paved in mid -October
1998.
* Golf course construction continues.
* Home construction on the first 61 production homes continue.
* Civil engineering on all the subdivisions north of Bollinger Canyon Road is in
progress-
* Landscaping on the entry feature, the Bollinger Canyon Road streetscape and the
internal streets of Subdivisions 7979 and 7980 is in progress.
* Planning for the 1998/99 erosion control work is in progress.
3. ANTICIPATED EFFORTS FOR THE FOLLOWING THREE YEARS:
* Completing the mass grading; fall 1998 or spring 1999.
* Completing the golf course for a Fall 1999 opening. r
* Completing The Bridges golf course clubhouse (construction start September 1998)
and driving range.
AUU-US-88 WED 11:1 r S i NC LAND DEPT M NU. 08804b5 l N. U3
* Continuation Of the site development and home-building activities as the economy
and weather allow. Our goal is to have all subdivisions north of Bollinger Canyon Road
paved in 1999.
* Site development activities south of Bollinger Canyon Road will probably be started
within the next three years. Solid projections on timing in this area would be premature
at this time.
* Completing the Bollinger Canyon Road/ Dougherty Road intersection. Spring 1999.
* Completing the construction of the Elementary School ready for Fall 2000
occupancy. Construction start Summer 1999.
* Completing the 7.5 acre neighborhood park on Rosincress Drive at North Chanterelle
Drive. The rough grading of the park is complete. Lance construction drawings
will be prepared in the Whiter of 1998 with an anticipated start in Spring of 1999,
depending upon water availability.
* Completing the Falcon Bridge apartment complex.
* Completing the Coyote Creek revegetation work. The revegetation program is
anticipated to start in. September 1999 with planting to start in October 1999. The
revegetation program will follow the golf course construction until completion.
* We will be submitting for an additional 60 building permits within the next two
weeks. Generally we plan on 90 to 100 building permits per building product per year.
A five year absorption schedule was prepared and submitted to the City of San Ramon as
part of the County Service Area budget update.
4. SIGNIFICANT ACTIVITY RELATING TO PUBLIC AND PRIVATE
RiFRASTRUCTURE:
We continue to design and build the public infrastructure needed to serve our housing
construction. We are in continual contact with the City of San Ramon and the various
utility agencies responsible for providing sexvice to our homeowners. The only major
impediment to date affecting the provision of utilities is the time required to process plans
through the East Bay Municipal Utility District and Pacific Gras and Electric design
departments. The Only physical public improvement not installed as planned has been the
connection of Bollinger Canyon Road to Dougherty Road due to the complex balance of
hydrological and environmental jurisdictional issues.
5, ALL SIGNIFICANT RESIDENTIAL AND C0NfiVMRCtAL ACTIVITY:
As mentioned in previous sections we are in construction on 61 homes. The sales center
opened on July 25,1998 and the public response was quite positive. It is anticipated that
we will request and additional (approximate) 60 building permits. The only commercial
activity has been the on -site sales center. The golf course clubhouse construction is
anticipated to start in September 1998 and take 18 months to complete construction.
6. SCHEDULE 1: RELEVANT INFORMATION TO BE PROVIDE IN ANNUAL
COMPLIANCE REPORT:
Child Care: There have been no occupancies within the project to determine student
generation rates. The delivery of the fast elementary school is 25 months in the future.
•n,Uti UD-eo wtu 1 1 - 10 b 1 NU LHNV W 1 r Nn [W. gU0Ug040W r. U4
Design development of the elementary school and adjacent private child care facility is in
progress with the San Ramon Unified School District.
Community Center: There have been 76 dwelling units (15 models and 61 production
units) started to date_ There have been no -occupancies to date. We are certainly more
than 18 months prior to the issuance of the 3,666th building permit. No action is required
at this time. Five year projections by Shapell and Windemere anticipate approximately
3200 dwelling units in the fiscal year 2002-03.
Developed Parkland: The population at the current time within the newly developed
housing is zero. Over the next three years it is anticipated the population wilt be
approximately 926 individuals, (343 dwelling units X 2.7 pph=926). A population of 926
would require 6.48 acres of parkland , and a minimum of 2.77 acres of either
neighborhood or community park. The 7.5 acre neighborhood park on North Chanterelle
Drive is anticipated to be complete within the next three years. No fixrther activity is
required at this time.
Corporation Yard: 15 model homes are complete to date. 61 production Domes are under
construction. The location of the proposed corporation yard was approved by the City of
San Ramon earlier this year. The corporation yard is anticipated to be located adjacent to
the open space staging area west of the realigned Dougherty Road. Final design of this
area will be done with the grading plans for that phase. No f Lrther action is required at
Ws time.
Shapell Interim Fire Station: No action required. It has been determined that all of our
phase I, The Bridges at Gale Ranch, is within an acceptable response boundary. The San
Ramon Fire Protection District reviews and approves each individual construction phase
prior to building permit issuance.
Shapell Permanent Fire Station: No action required. This requirement was deleted
during the Gale Ranch phase 2/Windemere 1 entitlement process. If the Windemere
station is constructed in the designated location only one station is required in the
Dougherty Valley.
Flood Control Facilities: The flood control facility design was reviewed an approved by
the Contra. Costa County Flood Control District. The detention basin is located within
the golf course envelope north of Bollinger Canyon Road. That facility is complete.
Maintenance of the facility will be by the golf course operator in accordance with a
separate agreement with the City of San Ramon in accordance with the Memorandum of
Understanding.
Library: No action required. The issuance of the 3,666th building permit is still quite
some time in the future. Five year projections suggest the 18 month design trigger is still
at least four years in the future.
nuu- w uu wuw i t s 10 0111U LHAU UGr 1 r nn 1W. 4UO0 U4UU r re W;
Open Space Staging Area: The staging area location was reaffirmed the November 1996
Specific Plan Amendment. The proposed corporation yard is located adjacent to the
staging area, west of realigned Dougherty Road. Both locations have been approved by
the County and City.
Park and Ride Sites: The location of the major park and ride lot on the Shapell property
was reaffiumed during the 1996 Specific Plan Amendment. It is located in and will be
constructed with our phase 2.
Police Station; Interim Facility: The current new development population is zero. It is
anticipated the first phase The Bridges at Gale Ranch, can be easily served by the City of
San Ramon police station on Camino Ramon. No action needed at this time.
Police Station; Permanent Facility: Conceptually located in the Village Center the Police
station needs are being considered with the Community College design, being proposed
for the 'Village Center.
First Elementary School: Already in design in cooperation with the San Ramon Unified
School District the first elementary school is targeted for a Fall 2000 occupancy. There
are no school age generation figures yet available for The Bridges project Shapell
Industries intends to build the school and playing .fields and turn them over to the District
for operation.
First Middlc School: No action required. There have been no students generated within
the project limits. The mass grading of the noddle site has been started primarily due to
the need to integrate the grading with the adjacent elementary school site. The grading
will be complete only after additional design work has been done with the school district.
High School: No action required. There have been no high school students generated
within the project boundary. The high school is located within the Windemere project
boundary.
Senior Center: No action required. The issuauee of the 8,607th building permit is quite
distant. There have been 76 residential permits issued to date.
Should you require any additional information to determine the completeness and
acceptability of our 1998 Annual Compliance Report please do not hesitate to call.
Sincerely,
Chris Truebridge
Vice President
Shapell Industries of Northern California